A working Excel schedule built on the cost-to-cost percentage-of-completion method — the format your lender and surety expect. Fourteen sample jobs already filled in so you can see how it behaves before you put your own numbers in.
| Column | Calculation |
|---|---|
| % Complete | Cost to date ÷ current budget |
| Earned revenue | Final contract × % complete |
| Over / (under) billing | Earned revenue − billed to date |
| Backlog | Final contract − billed to date |
Blue cells are inputs. Everything else calculates, so changing a budget or a cost updates the whole schedule. Built on the cost-to-cost percentage-of-completion method that lenders and sureties expect.